Granite Announces Arlington Avenue Bridges Replacement Project in Reno, NV; Groundbreaking Included U.S. Secretary of Transportation Pete Buttigieg

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) is proud to announce its role as Construction Manager at Risk (CMAR) of the Arlington Avenue Bridges Replacement Project, a transformative initiative aimed at replacing the two structurally deficient bridges that cross the Truckee River in the Riverwalk District of downtown Reno, Nevada. The approximately $32 million project was awarded by the Regional Transportation Commission (RTC) of Washoe County and is funded by federal and local fuel tax funds.

At the groundbreaking event last week, U.S. Secretary of Transportation Pete Buttigieg emphasized the significance of the project, stating, “These bridges are structurally deficient, but they are also profoundly important. They serve as was said the beating heart of this city and are such an important part of both the function and the quality of life of this community.”

The Arlington Avenue Bridges Replacement Project will involve working within the waterway, utilizing two diversions to complete the necessary work. The project’s primary goals are to address the deteriorating condition of the bridge structures, enhance safety for pedestrians, bicyclists, transit riders, and drivers, and ensure sufficient hydraulic capacity for the Truckee River during flood events.

Key Highlights of the Project:

  • Safety Improvements: Enhanced safety measures for pedestrians, bicyclists, kayakers, transit riders, and drivers in the Wingfield Park area.
  • Structural Replacement: Replacement of the two nearly century-old Arlington Avenue bridges that have become structurally deficient
  • Hydraulic Capacity: Improved hydraulic capacity to manage flood events effectively.
  • Roadway and Utility Upgrades: Roadway improvements, utility upgrades, and relocations.
  • Aesthetic Enhancements: New lighting, landscaping, and aesthetic improvements to enhance the visual appeal of downtown Reno.

“The Arlington Avenue Bridges Project is a signature initiative that will significantly enhance the landscape of downtown Reno,” explained Chris Burke, Granite Vice President of Regional Operations. “This project not only provides excellent backlog for Granite in Reno, but also strengthens our relationship with local entities through collaboration during the preconstruction phase,” he continued.

Granite initiated a series of partnership meetings with team members to foster early collaboration, which proved crucial for effective project management. During preconstruction and various design stages, Granite reviewed plans, specifications, and quantities, held risk and innovation workshops, and conducted resolution meetings to clarify work requirements. This collaborative CMAR process resulted in a collective saving of $7 million on the budget, a plan to complete all in-river work in one season, and a reduction of six months from the initial schedule.

Granite will provide materials from its nearby Lockwood Facility, including 10,000 tons of granular backfill for bridge structures earthwork, 9,000 tons of structural backfill for bridge structures earthwork, 1,400 tons HMA for roadway reconstruction, and 1,800 tons AB for roadway reconstruction.

The construction portion of this project is expected to begin in May 2025 and be completed in August 2026.

About Granite

Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite on LinkedIn, X, Facebook, and Instagram.

Contacts

Granite Contacts
Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

Granite

NYSE:GVA

Release Versions

Contacts

Granite Contacts
Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

More News From Granite

Granite Wins $114M Award for Next Segment of Highway 101 Project 

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been awarded Segment 4E North of the Highway 101 Carpinteria to Santa Barbara Construction Manager/General Contractor (CM/GC) project by Caltrans. Granite is the construction manager for the entire phase 4 project, and was previously awarded Segment 4E South in 2024. The contract award is approximately $114M. The Carpinteria to Santa Barbara CM/GC is a major, multi-year program to increase safety and reduce con...

Granite Secures $495M in Tactical Infrastructure Work

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been awarded the LRT-4 Webb-Zapata project by Customs and Border Protection. The approximately $495M project will be included in the company’s first quarter 2026 CAP. The project scope consists of 27 miles of tactical infrastructure improvements near Laredo, Texas. This includes significant mass excavation, grading, roads, as well as fencing and cattle guards. Granite will construct seven bridges, eight major c...

Granite Earns Handshake Early Talent Award for Sixth Consecutive Year

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) has been named a Handshake Early Talent Award recipient for the sixth consecutive year, reaffirming the company’s commitment to attracting, developing, and retaining early career talent. The Handshake Early Talent Award recognizes employers that consistently engage students and recent graduates through meaningful career opportunities, inclusive hiring practices, and long-term professional development. Granite’s early career programs provi...
Back to Newsroom