Granite Joint Venture Continues to Win Contracts for Major Bridge Rehabilitation Project in Sacramento

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced that the American River Constructors (ARC) joint venture team comprised of Granite and California Engineering Contractors has been awarded another contract by the California Department of Transportation (Caltrans) for the American River Bridge Rehabilitation Construction Manager/General Contractor (CM/GC) project in Sacramento, California. A CM/GC Preconstruction Service contract has been underway since January 2021 and will be complete by the end of 2022. In addition, two child contracts totalling $20 million have been executed for access, clearing, and steel piling and girder procurement. The newest contract is a $50 million child project to construct the substructure for the bridge widening, and started construction in June.

The American River Bridge, located on State Route 51 from post mile 2.0 to 3.5, is a six-lane multi-span bridge constructed in 1954 and widened in 1965. The rehabilitation project will replace the bridge deck, protect the abutments and piers from scour, and provide a multimodal connection between downtown and eastern Sacramento. The scope of work includes the removal and replacement of the existing concrete deck and steel girder post-tensioning systems in spans one and two, and the widening of the bridge to accommodate traffic during construction. ARC will also construct a class 1 bike path along the bridge that will connect to existing bike trails.

“The Caltrans/ARC Project Team has come together very quickly as a world class team, and has done an amazing job of working together to design and deliver these child projects,” said George Delano, Granite project executive. “This Team has accomplished the nearly impossible task of addressing all regulatory and environmental permitting issues to allow a June 2022 construction start in the floodplain. The communication, collaboration, and responsiveness with the various permitting agencies have been the key to that success.”

CM/GC procurement includes the contractor during the design and planning phases and offers a lower risk profile for both the contractor and the owner while increasing the overall value to project stakeholders. This process is designed to promote collaboration and to solicit value-adding feedback from the contractor.

Preconstruction is underway and construction is expected to conclude in December 2025.

About Granite

Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite on LinkedIn, Twitter, Facebook, and Instagram.

Contacts

Media
Erin Kuhlman 831-768-4111

Investors
Wenjun Xu - 831-761-7861

Granite

NYSE:GVA

Release Versions

Contacts

Media
Erin Kuhlman 831-768-4111

Investors
Wenjun Xu - 831-761-7861

More News From Granite

Granite Awarded Preconstruction Services Agreement for Progressive Design-Build Project on I-80 East in Nevada

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) today announced that the Nevada Department of Transportation (NDOT) has selected the company to deliver preconstruction services for the future Interstate 80 (I-80) East Widening Project along the 13-mile corridor between Vista Boulevard and USA Parkway in Washoe County. The approximately $19 million preconstruction services agreement represents a major milestone toward the delivery of the anticipated $475 million construction phase, fund...

Granite Declares Quarterly Dividend

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) today announced that its Board of Directors has declared a quarterly cash dividend of $0.13 per common share. The dividend is payable on April 15, 2026, to all shareholders of record at the close of business on March 31, 2026. About Granite Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as wel...

Granite Reports Fourth Quarter and Fiscal Year 2025 Results

WATSONVILLE, Calif--(BUSINESS WIRE)--Granite (NYSE: GVA) today announced results for the quarter and year ended December 31, 2025. Fourth Quarter 2025 Results Net income totaled $52 million, or $1.03 per diluted share, compared to net income of $41 million, or $0.84 per diluted share, for the same period in the prior year. Adjusted net income totaled $65 million, or $1.40 per diluted share, compared to adjusted net income of $56 million, or $1.23 per diluted share, for the same period in the pr...
Back to Newsroom