Report: Colorado’s Solar Permit Processes Lag Behind Best Practices

Advocates Support ‘Fair Permit Act’ to Clear the Way for Colorado Solar Market, Job Growth

DENVER--()--The Vote Solar Initiative (Vote Solar) and the Colorado Solar Energy Industries Association (COSEIA) today released a report and online interactive map rating solar permitting practices in 34 cities and counties across Colorado. Local solar permitting practices have a significant impact on the cost of solar energy systems for homes and businesses.

The new report indicates that, although practices vary widely by municipality or county, the average fee for Colorado solar permitting is nearly twice as high and seven times longer than national permitting best practices. The findings reinforce the need for Colorado to adopt the standardized, streamlined solar permitting practices contained in the Fair Permit Act of 2011 (HB10-1199) and to keep working to simplify permitting processes to drive down costs for consumers.

“With a clear policy commitment to renewables in place, Colorado has become one of the nation’s most promising solar markets. However, the state has an inefficient permitting landscape that directly undermines its renewable energy and economic development goals. Removing red tape and unnecessary fees from the solar permitting process is one simple and effective way that local governments can support Coloradan investment in clean energy,” said Gwen Rose, Deputy Director of Vote Solar and lead author of the report.

Added RJ Harrington, COSEIA’s Policy Director, “While there are certainly examples of leadership on the issue, many of Colorado’s cities and counties have permitting processes that add extraneous costs for solar customers and add unnecessary administrative work for solar installers and public agencies alike. Coloradans need the Fair Permit Act to help clear the way for solar adoption and economic development.”

When a Colorado energy customer invests in a solar electric or solar thermal system, that resident, business or other organization must first apply for and obtain a permit from the local government. According to best practices, this process should be transparent, standardized, expeditious, and reflect the municipality’s actual cost of review and issuance. As today’s report indicates, costs still vary widely by municipality due to different permitting plan review processes and other extraneous fees. This has resulted in piecemeal, local permitting practices that are often costly, complex, non-transparent and time-intensive.

The Fair Permit Act (HB 11-1199) is designed to reduce Colorado’s local solar permitting costs and clear the way for increased in-state investment in solar and related economic development. Specifically, the Colorado Fair Permit Act would:

• Extend existing $500 and $1,000 permit fee limitations to the plan review and permit issuance process for solar energy systems under 2-megawatts (MW) in size – these are currently set to expire on July 1, 2011

• Reduce unnecessary costs by limiting' plan review and permit issuance fees to their actual costs for solar energy systems larger than 2 MW in size.

• Promote transparency by ensuring local governments clearly and individually identify all fees and taxes assessed on an invoice.

Using industry-standard best practices as a benchmark, Vote Solar and COSEIA assessed each city for the time and cost associated with solar permitting. The report found that permit fees for an average-sized residential solar system can cost a whopping $2,000 and take as many as 20 business days. The average cost of a solar permit in Colorado is $495 compared to a best practice fee of $250 or lower. Additionally the average time-to-issuance in Colorado is seven business days, significantly longer than the recommended over-the-counter practice. However, those local practices vary widely across the state. Breckenridge, Colorado Springs, Denver, Denver County, Grand Junction and Pueblo lead in solar-friendly permit practices. Meanwhile, Arapahoe County, Aurora, Commerce City, Douglas County, Erie and Longmont showed the most need for improvement.

Colorado is the second state in Vote Solar’s Project: Permit, a campaign to highlight and improve solar permitting practices in cities nationwide. To view the Project: Permit map, full Colorado report, and best practice guidelines, visit: http://votesolar.org/solar-map/

About the Vote Solar Initiative: Vote Solar is a non-profit grassroots organization working to fight climate change and foster economic opportunity by bringing solar energy into the mainstream. Since 2002 Vote Solar has engaged in state, local and federal advocacy campaigns to remove regulatory barriers and implement the key policies needed to bring solar to scale. www.votesolar.org

About the Colorado Solar Energy Industries Association: Established in 1989, COSEIA is the nonprofit association leading Colorado's solar industry. Its mission is to expand the use of solar technologies across Colorado. COSEIA advances solar policy, removes market barriers, highlights emerging trends, and improves education and outreach. www.coseia.org

Contacts

The Vote Solar Initiative
Rosalind Jackson, 415-817-5061
rosalind@votesolar.org

Release Summary

Vote Solar and COSEIA released a report and online interactive map rating the cost and time of acquiring a solar building permit in 34 cities and counties across Colorado.